Atlanta Electricals Limited (ATLANTAELE) Q2 Results FY27 Preview: Date, Time, Expectations & Key Things To Watch

Cofacto Research Published October 27, 2026 6 min read

Atlanta Electricals Limited manufactures power, auto, inverter duty and special duty transformers from 5 MVA/11 kV up to 500 MVA/765 kV, serving utilities, renewables and industrial customers from five facilities with 63,060 MVA of combined capacity. The Q2 print will speak to whether EBITDA margin can move toward the 17-18% FY27 guidance after Q1's 16.5%, and whether order intake holds the ~Rs. 700 Cr quarterly run-rate in what management flagged as a peak order-booking period.

Quick Details
Results dateOctober 31, 2026
QuarterQ2 FY 2026-2027
Previous quarter revenueRs. 466.33 Cr (+48.0% YoY)
Previous quarter PATRs. 46.84 Cr (+50.4% YoY)
Previous quarter EBITDA margin16.5%
Market capRs. 12,578.44 Cr
CMPRs. 1,634.30

Atlanta Electricals Limited Q2 Results Date and Time

The board is scheduled to meet on Saturday, 31 October 2026 to approve the unaudited standalone and consolidated financial results for Q2/H1 FY27 (quarter and half year ended 30 September 2026), along with other business. The trading window, per the 25 September 2026 letter, remains closed till 48 hours after results declaration under SEBI's insider trading code.

What to expect from Atlanta Electricals Limited's Q2 FY27 results

Atlanta Electricals enters Q2 FY27 with a Rs. 3,116.63 Cr order book as of 30 June 2026, up 25.0% QoQ, and management has flagged Q2 and mid-Q3 as peak order-booking periods against a ~Rs. 700 Cr quarterly intake run-rate. The central question for the quarter is the EBITDA margin bridge: Q1 printed 16.5% against the 17-18% FY27 guidance, while copper rallied from around $13,000/t in early July to a record $14,533/t in early September and the rupee traded at 95.6-95.9 through the window versus 87.91 a year earlier, inflating dollar-linked copper and imported CRGO landed cost. About 70% of utility orders carry price-variation pass-through, but with job-to-job procurement and inventories of just Rs. 364.13 Cr at 31 March 2026, there is little low-cost stock buffer, so input inflation should flow into Q2 cost of materials before pass-through catches up. On execution, the 765 kV technology tie-up was targeted to close in Q2 FY27 (USD 3-5 million one-time fee plus 2-4% royalty), with Q3 FY27 earmarked for raw material injection and production, and the APTRANSCO LoI of Rs. 193.92 Cr received on 18 August 2026 sits inside the quarter window. The bushing shortage remains an execution overhang, with management having said the situation could potentially complicate further before easing, and net working capital days are guided to rise to 80-90 in FY27-FY28 from 64 in FY26. The call should also cover Unit 6 IDT commissioning progress toward the December-end target and conversion of the first 400 kV order at Vadod Unit-IV.

Key Things To Watch

Performance vs guidance tracking: Q1 FY27 revenue grew 48.0% YoY, ahead of the ~40% FY27 growth path, while EBITDA margin of 16.5% sits below the 17-18% FY27 target.

  • FY27 revenue growth — ~40% on the Rs. 1,851 Cr FY26 base — Q1 grew 48.0% YoY, tracking ahead
  • EBITDA margin — 17-18% for FY27 (also 16-16.5% public-offering-era range) — Q1 at 16.5%; watch whether Q2 moves toward 17-18%
  • Order book execution — ~Rs. 2,400 Cr of the Rs. 3,100 Cr unexecuted book in FY27; Q2 and mid-Q3 flagged as peak order-booking periods
  • Vadod Unit-IV utilization — ~65% in FY27 from ~39% in FY26

765 kV tie-up and 400 kV prototype progress

  • 765 kV technology tie-up targeted to close in Q2 FY27 — USD 3-5 million one-time fee plus 2-4% royalty on 765 kV class products; Q3 FY27 earmarked for raw material injection and production
  • First 400 kV transformer prototype at Vadod and short-circuit test status; PGCIL approval for up to 400 kV class received 2 April 2026
  • Execution of the Rs. 275 Cr 400 kV order book at Unit 4 Vadod

Unit 6 IDT and backward integration capex

  • Unit 6 inverter duty transformer facility (~5,000 MVA, Rs. 65 Cr capex) — commissioning targeted by end of Q3 FY27 (December end)
  • Tank and radiator backward integration (Rs. 170-180 Cr capex) — Rs. 15-20 Cr invested so far; commencement targeted during FY27 near the Vadod facility

Margin bridge and input costs: Q1 FY27 gross margin declined QoQ on product mix (56% 220 kV, 25% 66 kV, ~5.5% 132 kV) and raw-material pricing pressure.

  • Copper rose from ~$13,000/t in early July to a record $14,533/t in early September before fading below $14,000/t; rupee at 95.6-95.9 vs 87.91 a year ago inflates imported CRGO cost
  • ~70% of utility orders carry price-variation pass-through; management expects margins to remain sustainable at 17-18% despite raw-material increases that may persist
  • Whether management reiterates, trims, or re-anchors to the 16-16.5% public-offering-era margin framing

Order intake, bushing supply and working capital

  • Order intake vs the ~Rs. 700 Cr/quarter run-rate; APTRANSCO LoI of Rs. 193.92 Cr (~6.22% of Q1FY27-end backlog) conversion to formal order; export bookings against the 15%-of-revenue target
  • Bushing shortage status — management earlier said the situation could potentially complicate further before easing; check for delivery schedule slippage
  • Net working capital days trending toward the 80-90 guide (from 64 in FY26); whether the subsidiary's Rs. (4.40) Cr Q1 loss on nil revenue persists

Frequently Asked Questions

Why does Atlanta Electricals' EBITDA margin matter so much this quarter?

Q1 FY27 EBITDA margin was 16.5%, below the 17-18% FY27 guidance, on a 220 kV-heavy mix and raw-material pricing pressure. Copper touched a record $14,533/t in early September and the rupee was around 9% weaker year-on-year, so the margin bridge back toward guidance is the key question for Q2.

How big is Atlanta Electricals' order book and what does management plan to execute from it?

The order book stood at Rs. 3,116.63 Cr as of 30 June 2026, up 25.0% QoQ and 96.76% higher than the Rs. 1,584 Cr level of 30 June 2025. Management has guided to executing about Rs. 2,400 Cr of the roughly Rs. 3,100 Cr unexecuted order book in FY27.

When will the 765 kV technology tie-up be finalised?

Management has targeted closing the 765 kV technology tie-up in Q2 FY27, with Q3 FY27 earmarked for raw material injection and production, followed by Power Grid revalidation. The terms involve a fixed one-time fee of USD 3-5 million upon successful development plus a 2-4% royalty for three to four years on 765 kV class products.

Is Atlanta Electricals on track with its FY27 revenue growth guidance?

Management has guided to about 40% revenue growth in FY27 on the Rs. 1,851 Cr FY26 base, and a 40% CAGR over the next three years. Q1 FY27 revenue grew 48.0% YoY to Rs. 466.33 Cr, tracking ahead of that path.

What happened with the SBPDCL debarment against Atlanta Electricals?

SBPDCL's debarment order dated 24 April 2026, which stemmed from a single observation during a CPRI Bhopal post-test inspection with no established design failure or systemic quality issue, was withdrawn in its entirety with immediate effect on 13 August 2026 following the company's representations. The upcoming call may confirm no new customer-quality or regulatory issues have emerged since.