Nuvoco Vistas is a cement maker with 27 MMTPA of capacity across East and North India, heading into a quarter where the Vadraj/Kutch complex in Gujarat begins phased commissioning from Q3 FY27. The print will speak to whether EBITDA/ton holds near management's ~INR 900 target amid fuel and packing cost pressure, and how the company's margin and volume trajectory tracks its mid 7%-8% FY27 volume growth goal.
| Results date | October 22, 2026 |
|---|---|
| Quarter | Q2 FY 2026-2027 |
| Previous quarter revenue | Rs. 3,128.71 Cr (+8.91% YoY) |
| Previous quarter PAT | Rs. 159.63 Cr (+19.88% YoY) |
| Previous quarter EBITDA margin | 18.26% |
| Net debt (latest quarter) | Rs. 4,595 Cr (June 2026) |
| Market cap | Rs. 12,184.38 Cr |
| CMP | Rs. 341.15 |
A board meeting is scheduled on October 22, 2026, to approve the Q2 and H1 FY27 financial results. The trading window for designated persons has been closed from October 1, 2026, until 48 hours after the results declaration.
An analyst/investor conference call for Q2 and H1 FY27 is scheduled for October 23, 2026, at 3:30 PM IST, the day after the results.
The key test this quarter is whether EBITDA/ton lands near management's guided ~INR 900 (per ton) for Q2 FY27, against a derived Q1 FY27 level of ~Rs. 1,079/ton, with management having guided variable cost up ~INR 100 QoQ on power and packing costs. The pricing assumption behind that guide is under scrutiny: the all-India average trade price for Q2FY27 was Rs. 351/bag, down Rs. 1/bag sequentially, with East and North recording only Rs. 5/bag September increases, while petcoke rose ~8-9% MoM in August to USD 146-147/t — though raw jute easing from Rs. 19,000 to ~Rs. 12,500/quintal by mid-September supports the guided Rs. 20-25 bag-cost cooling. On volume, core-sector cement output grew 12.5% YoY in August 2026 and industry offtake is estimated at 6-7% YoY in July-August, making the company's mid 7%-8% FY27 volume growth target look trackable off a soft Q2 FY26 base of 4.3 MMT, with rake availability and East India rainfall the swing factors. Beyond the quarter, the Vadraj/Kutch complex remains pivotal, with Kutch CU trial preparation and GU civil works targeted within Q2 FY27 and phased commissioning from Q3 FY27, alongside a debt goal within 2x to 2.5x EBITDA by end-FY27 from net debt of Rs. 4,595 Cr at June 2026. The call is also the first results reviewed under new statutory auditor Walker Chandiok & Co LLP.
Performance vs guidance tracking: Key guidance items management has on record going into the Q2 FY27 print:
Margin trajectory vs the ~INR 900/ton Q2 target
Kutch/Vadraj commissioning milestones
Gujarat build-out and East ramp
Risk and governance follow-ups
Management declined to guide on future EBITDA/ton, saying 'that's not be appropriate', but cited geo-mix, premiumization, trade/non-trade and blended cement as durable strengths. EBITDA/ton has ranged INR 700-900/ton over the last 6 years, and per management the last two quarters have been 'in range towards INR 1,000 and higher'.
The CFO attributed the rise from Rs. 4,217 Cr to ~Rs. 4,445 Cr to the Rs. 1,800 Cr Vadraj investment, Rs. 200 Cr VEGL investment, and Rs. 900 Cr CCD proceeds used to repay CP/bridge. On a like-for-like basis, net debt reduced by Rs. 300 Cr from 'operational efficiency, prudent capex and cash flow generation'.
Management said current blended hikes of INR 10-12/bag 'just about meet the current kind of cost inflation', against a post-GST headroom of INR 35-37/bag cited in Q&A. Price hikes are deemed essential to offset fuel and packing cost rises industry-wide.
The MD has guided to 'mid 7%-8%' volume growth for FY27, close to expected market growth of 7%-9%, with incremental volume from Gujarat adding to a strong North. This implies incremental sales volume of 1.75 to 2 million tons versus FY26's record 20.4 MMT.
As of the Q1 FY27 call, Kutch CU kiln rotation was complete and ready for brick lining, Kutch GU VRM equipment installation was complete, and CU trial preparation was targeted within Q2 FY27 with GU civil works completion by Q2 FY27. Phased commissioning begins Q3 FY27, with full commissioning targeted Q3 FY27-Q1 FY28.