Q1 FY27 earnings call · July 28, 2026

Tata Power Q1 FY27 Earnings Call: Targets Rs. 30,000 Cr Rooftop Revenue, Mundra Plant to Operate Until 2038 (TATAPOWER)

Cofacto ResearchPublished July 28, 20267 min read
Quick summary

Tata Power Company Ltd held its Q1 FY27 earnings call on July 27, 2026. Here's a quick read of what management said — performance, strategy, and the outlook ahead.

Record Quarter Extends 27th Consecutive Growth Streak

  • PAT of Rs.1,401 crore — rose 11% YoY in Q1 FY 2026-2027, marking the 27th consecutive quarter of PAT and EBITDA growth for the company.
  • EBITDA of Rs.4,209 crore — up 8% YoY in Q1 FY 2026-2027, supported by broad-based expansion across renewable, transmission, and manufacturing segments.
  • 4-year revenue CAGR of 8% — with EBITDA CAGR of 12% and PAT CAGR of 7% over the same period, reflecting sustained margin expansion.
  • Net debt-to-underlying EBITDA at 3.41x — and net debt-to-equity at 1.25x; both metrics within internal guardrails as of Q1 FY 2026-2027.
  • Coal profits contributed Rs.225 crore PAT — in Q1 FY 2026-2027, partially offset by Mundra generation losses recovered via the STPA mechanism (fixed cost + coal pass-through), with management targeting no loss on ROE.

Module Production Crosses 1 GW; Rooftop Surges Toward Rs.30,000 Cr Target

  • TP Solar module output exceeded 1,000 MW — in Q1 FY 2026-2027 for the first time, with the plant operating at full capacity; cell output dipped temporarily due to a line change for higher-efficiency products, with yield expected to improve by Q2 FY 2026-2027.
  • TP Solar margin sustained at ~25% — in Q1 FY 2026-2027; management expects consistency as the plant stabilizes, citing ability to command a premium for high-efficiency cells despite new industry capacities.
  • Rooftop solar revenue reached Rs.1,350 crore — in Q1 FY 2026-2027 on 371 MW installed; order inflow stood at Rs.1,091 crore on 387 MW. Management guided for 60-70% growth in FY 2026-2027.
  • Targeting Rs.30,000 crore rooftop revenue by FY 2028-2029 — management states it is "targets crossing Rs.30,000 crore in rooftop solar revenue by FY 2028-2029, earlier than the initial 2030 target," versus Rs.4,800 crore in FY 2025-2026.
  • Market share ambition: 12-13% to 25% — management aims to nearly double rooftop solar market share within the same timeframe (FY 2028-2029); the next-largest competitor holds only 2%.
  • Monthly installations surged from 1,000 to 30,000 units — over the past two years (Q1 FY 2026-2027); management sees headroom with only 40 lakh consumers out of 250 million having adopted rooftop solar in India.
  • Renewable capacity at 6.7 GW — targeting 2.5 GW additions in FY 2026-2027 to cross 9 GW by year-end; commissioned 226 MW in Q1 FY 2026-2027 with line of sight for ~500 MW in Q2 FY 2026-2027.

Mumbai Transmission Drives Rs.10,000 Cr Plan; Odisha Discom Faces Timing Headwinds

  • Transmission segment 4-year revenue CAGR of 45% — with EBITDA CAGR of 19% and PAT CAGR of 27%; Mumbai transmission plans a Rs.10,000 crore investment over the next 5 years, with regulatory approval received and projects under implementation.
  • Odisha Discom PAT grew 6% in Q1 FY 2026-2027 — with million units sold up 10.4% due to hot summer; management attributed muted growth to delayed government payments for Panchayati Raj departments, a government-mandated no-disconnection policy during the heatwave, and a one-month billing cycle, with recovery expected in Q2 FY 2026-2027.
  • Delhi Discom lower collections due to seasonal billing cycles — management explained high summer consumption will be billed later, calling the issue non-structural and noting performance normalizes over a 12-month cycle.
  • TBCB projects reported 13% EBITDA margin in Q1 FY 2026-2027 — because all projects are still under construction; current revenue comes from lease accounting for engineering work, not operational asset profits. First projects expected to commence contributions from Q2 FY 2026-2027.
  • Rithala plant closed since 2016 — fully settled with provisions made, hence not listed in operating capacity; tariff and depreciation issues led to the closure.

Rs.25,000 Cr Capex Plan on Track; Pumped Hydro & Mundra Anchor Long-Term Growth

  • Q1 FY 2026-2027 capex of Rs.5,300 crore — against the full-year plan of Rs.25,000 crore (50% allocated to renewables); management reported clear line of sight on execution. Q2 FY 2026-2027 capex guided at Rs.6,000-6,500 crore, with nearly half for renewables as 800-900 MW of capacity is targeted for commissioning.
  • Pumped storage pipeline of 2,800 MW — targeted for completion in FY 2029 and FY 2031; a 330 MW unit won via SECI bid, and the balance 1,800 MW project work begins later in FY 2026-2027, with commissioning starting CY 2029. Management plans to announce the next set of projects within 12 months.
  • Mundra plant expected to operate continuously until 2038 — operating under Section 11; cabinet approvals expected from three states in August 2026 and a fourth by September 2026. The supplementary PPA is cost-reflective with no margin and no return on equity.
  • Kholongchhu hydro project (Bhutan) PPA signed — with regulatory approval, "expected operational in CY 2030," per management.
  • 1,125 MW road drilling project — financial closure expected within Q2 FY 2026-2027 with PFC, IFC, and other lenders.
  • Nuclear: preliminary work underway — land, geotechnical studies, and water availability assessments in progress; a firm plan is subject to government rules notification.
  • Q1 capex allocation: 40-45% to renewables — capex also accelerating for pumped storage and transmission, including a Rs.2,000 crore, 2,000 km+ pipeline for Mumbai transmission.

Tata Projects Nears Legacy Clean-Up; Solar EPC Wind-Down Weighs on Comparables

  • Tata Projects widening losses due to final 10% of legacy projects — Dr. Sinha expects a potential impact for "possibly one more quarter" before a turnaround, supported by a strong pipeline of orders from global marquee clients.
  • Solar EPC business discontinued in FY 2026-2027 — management is wrapping up remaining work and booking losses (compared to ~Rs.100 crore PAT in FY 2025-2026 from EPC); resources repurposed to the in-house 5.5 GW project pipeline.
  • International coal prices rose 5-7% in Q1 FY 2026-2027 — management expects a further uptick of up to 5% over the next nine months (through Q1 FY 2027-2028). KPC has met Indonesian domestic market obligations; no major disruptions expected from new regulations.
  • Industry-wide RE curtailment of ~5% in Q1 FY 2026-2027 — management expects this to settle in the "next few quarters" as transmission and evacuation lines progress.
  • Government confirmed ALMM 2 continues — "Government clarified that ALMM 2 continues for rooftop and utility-scale projects, with a special proviso for certain projects only"; management confirmed their commitment to building ingot and wafer capacity remains on track.
  • RE auction volumes slowed in Q1 FY 2026-2027 — management explained state discoms are moving from central agency (SECI) tenders toward customized FDRE (round-the-clock renewable) bids, causing a temporary dip.
  • Pumped storage to use hybrid contract model — part annuity-based long-term bids, part bilateral negotiations with large industrial customers (e.g., Tata Steel); management is avoiding central agency PPAs and building directly to states.

Clear Line of Sight on FY27 Targets; Regulatory Milestones Define Near-Term Catalysts

  • Rooftop solar revenue guided at 60-70% growth for FY 2026-2027 — with a long-term target of Rs.30,000 crore by FY 2028-2029; management sees no threat to distribution or IPP businesses, as those models will evolve with technology.
  • Renewable capacity to cross 9 GW by end of FY 2026-2027 — driven by 2.5 GW of new additions; Q2 FY 2026-2027 commissioning target of ~500 MW (already ~226 MW completed in Q1).
  • Mundra: cabinet approvals from three states in August 2026, fourth by September 2026 — plant expected to run continuously until 2038 under Section 11, with cost-reflective PPA and no ROE.
  • TP Solar cell yield improvement expected by Q2 FY 2026-2027 — after a temporary decline due to a line change for higher-efficiency products; module production already at full capacity (1,000 MW+ in Q1).
  • Next set of pumped storage projects to be announced within 12 months — complementing the current 2,800 MW pipeline (FY 2029 and FY 2031 completion).
  • Risk: coal price upside of up to 5% over next nine months — through Q1 FY 2027-2028, which could pressure Mundra recovery; management noted KPC has met domestic obligations, limiting regulatory disruption.
  • Risk: RE curtailment expected to persist for a few more quarters — though management expects settlement as transmission infrastructure catches up; industry-wide curtailment was ~5% in Q1 FY 2026-2027.

Ask about this

Ask Cofacto a question about this call. Answers cite filings and company data.