NHPC Ltd
NSE: NHPCCompany page on Cofacto
Open the NHPC Ltd page

NHPC Q2 FY27 Earnings Call: Subansiri Powers 33% Revenue Jump, Guides Rs. 10,000 Cr EBITDA Run-Rate

Cofacto Research Published November 05, 2026 8 min read
Listen to the earnings call

NHPC Ltd held its Q2 FY27 earnings call on November 04, 2026. Here's a quick read of what management said — performance, strategy, and the outlook ahead.

Subansiri Part-Commissioning Powers a Strong Quarter

  • Q2 FY 2026-2027 revenue of Rs.4,482 crore (+33% YoY) — driven by part commissioning of Subansiri Lower, higher Parbati-2 generation, and resumption of commercial operation of Teesta-5; H1 FY 2026-2027 revenue at Rs.8,291 crore (+26% YoY).
  • Q2 PAT of Rs.1,549 crore (+52% YoY) — H1 PAT at Rs.2,645 crore (+27% YoY); adding back the Rs.231 crore Teesta-4 provision, management confirmed adjusted Q2 PAT of ~Rs.1,700 crore, ~90% higher YoY.
  • Q2 PAF of 92.24% vs 78.58% in Q2 FY 2025-2026 — H1 PAF at 86.67% vs 81.10%; H1 generation of 23,741 MU (+14% YoY).
  • Subansiri cost step-up now in P&L — H1 finance cost doubled to Rs.1,162 crore (vs Rs.539 crore) and D&A rose to Rs.1,210 crore (vs Rs.877 crore) since part commissioning; other income fell ~31% to Rs.338 crore as the prior year included insurance claim income.
  • Incentives fell sharply — Q2 incentives of Rs.59 crore vs Rs.253 crore in Q2 FY 2025-2026 (secondary energy down 89%, PA-based incentives down 77%); H1 incentives down 47% to Rs.103 crore.
  • Water cess relief — generation expenses fell to Rs.552 crore in H1 FY 2026-2027 (from Rs.592 crore) after the Honorable High Court of Uttarakhand verdict in favor of NHPC removed water cess in Uttarakhand.

Four Stations Drove the Incremental Profit

  • Four power stations drove the major share of incremental Q2 PBT — per Director Finance Mahesh Kumar Sharma: Subansiri, Parvati 2, Parvati 3 and Teesta 5.
  • Parvati 2 swung Rs.380 crore YoY — Rs.215 crore PBT in Q2 FY 2026-2027 vs a Rs.164 crore PBT loss in Q2 FY 2025-2026; with Parvati 3 adding Rs.80 crore, the two delivered Rs.460 crore of incremental Q2 PBT. Parvati 2 lost Rs.149 crore at PBT level in FY 2025-2026 as a whole.
  • Subansiri contributed Rs.130-132 crore PBT in Q2 FY 2026-2027 — and generated ~300 million units above the proportionate design energy of its 4 commissioned units in H1, outperforming the normalized profit expected from 4 units.
  • Teesta-5 resumed commercial operation in July 2026 — 859 million units generated in Q2 FY 2026-2027 with top line of Rs.150-160 crore and PBT contribution of Rs.99-100 crore; the plant is limited to 9 months of generation in FY 2026-2027 after missing Q1.
  • H2 Teesta-V outlook is trend-based — management expects H2 FY 2026-2027 generation similar to Q2's 859 million units with profit of Rs.100-150 crore, cautioning that hydro generation is very difficult to estimate; last-5-years average is 70% of generation in H1, 30% in H2.

Parbati-2 and Subansiri Tariff Decisions Are the Near-Term Catalysts

  • Parbati-2 revenue recognized at 80% to date — Rs.500 crore (20% balance) unrecognized as of Q2 FY 2026-2027; the CRC's next hearing on 11 November 2026 (Q3 FY 2026-2027) is expected by management to be the final hearing, with the order expected soon after reservation.
  • Parbati-2 full-tariff economics (period unspecified) — expected AFC of ~Rs.2,400 crore on design energy of 3,125 million units at ~Rs.8.5/unit; regulated equity ~Rs.4,000 crore (30% of Rs.13,600 crore capital cost); expected PAT ~Rs.680 crore at 17% core ROE, with 4-5% additional incentive ROE at management's discretion in models; typical EBITDA margin of 60-65% of top line.
  • Subansiri interim tariff order reserved — petitions filed for all 8 units and updated for 4 commissioned units; revenue currently booked at 18% of the filed tariff petition (Subansiri and Parvati booked at 80% of cost).
  • Subansiri full economics — capital cost of Rs.30,000 crore with Rs.23,000-24,000 crore capitalized for 5 units; levelized tariff ~Rs.8/unit; expected AFC of Rs.5,500 crore on full commissioning; expected PAT of Rs.1,500-1,600 crore from FY 2028-2029 onwards (regulated equity ~Rs.9,000 crore, 17% core ROE plus 4-5% incentives).
  • NHDC PSP will be regulated (as of now) — given the JV structure with the Government of MP; the PPA with the Government of MP is still under discussion and not finalized; project cost estimated at Rs.5,200 crore (period unspecified) with tariff currently estimated at Rs.4.9/unit, below Rs.5 (period unspecified).

1,744 MW Guided for FY 2026-2027; Heavy Hydro Award Pipeline Ahead

  • Subansiri Lower (2,000 MW): 1,250 MW commissioned — 5 of 8 units (unit 5 on 23 October 2026); two more units targeted in FY 2026-2027 and the final unit expected by June 2027 (FY 2027-2028); anticipated cost Rs.30,072 crore with ~90% (Rs.26,900 crore) spent till September 2026 and no further cost increase anticipated.
  • FY 2026-2027 commissioning guided at 1,744 MW — 500 MW Subansiri, 624 MW Kiru, 120 MW Rangit; FY 2027-2028 to add 1,000 MW Pakal Dul and 250 MW Subansiri; a further 1,390 MW and 1,000 MW expected over the next 4 years.
  • Kiru (624 MW) at 92% progress — reservoir filling starting November 2026, all units targeted by March 2027 (FY 2026-2027); Pakal Dul (1,000 MW) at 89% progress with reservoir filling planned end-December 2026 and two units targeted by March 2027 (FY 2026-2027).
  • Dibang (Rs.31,876 crore) on track for February 2032 completion — all major contracts awarded, Nala diversion achieved, Rs.5,504 crore spent; management "100% sure" of the date. Teesta 6 (500 MW) at 74% progress with commissioning expected September 2029 (FY 2029-2030); tunnel work is the only hurdle.
  • New awards: Kamale (1,720 MW) CCEA approved at Rs.26,070 crore in April 2026 — JV with Government of Arunachal in formation; Etalin (3,097 MW) has all clearances with cabinet approval expected within ~2 months (Q4 FY 2026-2027); Savalkot (1,800 MW) PIB completed with CCA approval pending, possibly by December 2026.
  • Pumped storage: 18 GW of PSPs in DPR/PFR stage — across Maharashtra, Odisha, MP, Gujarat and Andhra; management is hopeful at least two PSPs start physical work in FY 2027-2028; the 640 MW Indira Sagar-Omkareshwar PSP tendering is initiated with work commencement hopeful in FY 2026-2027.
  • Evacuation risk seen as low — transmission for Arunachal hydro projects is the CTU's responsibility, with lines awarded via tariff-based competitive bidding run by PFC and REC timed to each project's commissioning date; management stated there is no problem in evacuating power from the Arunachal plants.

Solar Delays and a PPA Tie-Up Gap Cloud the RE Story

  • 1,190 MW of RE capacity under construction guided to be 100% completed in FY 2027-2028 — commissioning has been delayed due to connectivity availability, which management noted all solar projects are facing.
  • Solar CPSU scheme progress — 300 MW Bikaner commissioned; 100 MW Andhra Pradesh expected by January 2027 (FY 2026-2027) and 600 MW Gujarat by November 2027 (FY 2027-2028); 40 MW Ganjam and 150 MW Kerala floating solar expected by March 2027 (FY 2026-2027).
  • ARIA PPA gap is material — NHPC, as a Renewable Energy Implementing Agency, has tendered ~20,000 MW of bids (also referenced 23,000 MW) and awarded 73 projects, but PPAs are signed for only 9,000 MW; management expects ~5,000-7,070 MW of additional PPAs (period unspecified), leaving ~5,000 MW that may remain untied (period unspecified).
  • States reluctant to commit to 25-year PPAs — resource adequacy plans have become unclear after energy demand patterns changed drastically over the past year; management is reworking the configuration of awarded ARIA projects and will not construct projects without PPAs to avoid an "unnecessary dent" on its finances.
  • No solar hive-off before commissioning — management will evaluate options on its solar/green energy portfolio only after commissioning, remaining bullish on RE diversification and citing the PSU precedent of NTPC diversifying from thermal into RE.
  • Rs.800 crore Etalin consideration unpaid — the consideration for the project transferred from HJVN to NHPC (under Ministry of Power direction) will be paid to SGVNL only after PIB approval, which management expects "anytime now"; both boards have approved the transfer.

Self-Funded Growth; Rs.10,000 Cr EBITDA Run-Rate Targeted

  • Receivables normalized to Rs.1,159 crore as of 3 November 2026 — from ~Rs.4,300 crore at 30 September 2026 (vs ~Rs.2,500 crore at FY 2025-2026 year-end); only Rs.6 crore outstanding beyond 45 days and average debtor days at 51 days; CFO cited the 2023 Electricity Late Payment Surcharge rules: "beyond 75 days, we don't have a single penny pending."
  • Group debt of ~Rs.59,000 crore vs LTM EBITDA of ~Rs.7,000 crore — Rs.29,000 crore deployed in operational projects and Rs.20,000 crore in under-construction projects; since NHPC uses balance-sheet financing, construction debt does not burden operating cash flow.
  • EBITDA guided to reach Rs.10,000 crore — post full-year Subansiri Lower and Pakal Dul commissioning; management concurred that Pakal Dul, Kiru and Rangit come online in FY 2027-2028, affirming the ~Rs.10,000 crore run-rate.
  • Capex: FY 2026-2027 target of Rs.14,300 crore with Rs.6,500 crore achieved till Q2 — management hopeful given H2-weighted utilization (FY 2025-2026 closed at Rs.13,700 crore vs a Rs.13,000 crore target); FY 2027-2028 onward capex guided at Rs.14,000-15,000 crore per annum at consolidated level.
  • No fresh equity needed for FY 2027-2028 — management targets PAT of Rs.6,000-6,400 crore; with depreciation of Rs.3,000-3,500 crore, ~Rs.10,000 crore operating cash less ~Rs.1,800 crore dividend and Rs.2,000-3,000 crore debt repayment leaves ~Rs.4,000 crore+ annually for capex.
  • 10-year capex projection of Rs.1,11,000 crore — with an equity requirement of Rs.40,000 crore (~Rs.4,000 crore per year), which management said internal resources are sufficient to fund.
  • Dividend and collections — FY 2025-2026 total dividend of 16.10% (Rs.1.61/share); H1 FY 2026-2027 collections from beneficiaries at Rs.5,126 crore (vs Rs.4,764 crore in H1 FY 2025-2026).
Share on X · LinkedIn · WhatsApp

Disclaimer: This earnings call summary is published for educational and informational purposes only. It is not investment advice, not a recommendation to buy, sell or hold any security.

Powered by Cofacto — AI research platform for Indian stocks, every claim cited from primary filings

Login Now